Skip to content

Apartment Construction Progress

Construction Status as of October 21st 2020

  • Metal Siding complete
  • Rough electric complete
  • Balconies Installed 
  • Roof Deck and Community Room well underway
  • Planting and landscaping are underway 
  • Cabinetry being installed
  • Flooring being installed
  • Tile in bathrooms being installed
  • Heating and Cooling Complete
  • Electrical Complete

Construction Status as of Sept 1st 2020

  • Metal Siding complete
  • Rough electric complete
  • Balconies Installed 
  • Roof Deck and Community Room well underway
  • Cabinetry being installed
  • Flooring being installed
  • Tile in bathrooms being installed
  • Heating and Cooling Complete
  • Electrical Complete

Construction Status as of June 2020

  • Framing complete
  • Rough plumbing complete​
  • Rough electric partially complete
  • Metal siding 75% complete
  • Interior insulation started
  • Drywall started

4th Floor • West

4th Floor • East