Apartment Construction Progress
Construction Status as of October 21st 2020
- Metal Siding complete
- Rough electric complete
- Balconies Installed
- Roof Deck and Community Room well underway
- Planting and landscaping are underway
- Cabinetry being installed
- Flooring being installed
- Tile in bathrooms being installed
- Heating and Cooling Complete
- Electrical Complete